Client: FERROVIAL CONSTRUCCIÓN, CHILE, S.A.
Location: ROUTE 25, RUTAS DEL LOA.
Total excavation: 600.000 m3
Client: SACYR
Location: ROUTE F20, REGION VALPARAISO
Total excavation: 1.000.000 m3
Platform construction and access roads for AMAZON’s logistic depot.
Client: Dragados
Location: Bobes, Principality of Asturias (Spain)
Excavation:: 450.000 m3
Area:160.000 m 2
Year: 2021
Conditioning of the slope of the right abutment of a dam. (YESA, ESPAÑA)
Client: COALVI (ALDESA)
Location: (YESA, ESPAÑA)
Excavation: 710000 m3
Year: 2019
Construction of the industrial park BonArea - Épila - Zaragoza
Construction of the platform for a meat processing plant for BonArea
Cliente: bonArea
Localización: ZARAGOZA
Volumen total movido: 2350000 m3
Año: 2019
Évora high speed railway (Elvas, PORTUGAL)
Construction project for high speed railway Lisbon - Badajoz. Lot Alandroal – Elvas.
Client: Sacyr
Location: Portugal
Area: 3500000 m3
Year: 2020
High speed railway Vitoria-Bilbao-S.Sebastian.
Lot of the “Y” basque between Atxondo and Abadiño.
Client: Dragados
Location: Atxondo (Bilbao, España)
Excavation: 1500000 m3
Year: 2020
Powerplant substation platform
Platform for the installation of an electrical transfer station (FUNDAO, PORTUGAL)
Client: Sacyr
Location: Fundao (Portugal).
Excavation: 600000 m3
Year: 2019
A2 WARSAW - (POLAND)
Task A: Design and costruction of the A2 Motorway, Warsaw - Kukuryki, section "Lubelska intersection" - start of the Minsk Mazowiecki ring road, section I, aprox. extension of 5.6 km
Excavación: 1.000.000 m3
Task B: Design and costruction of the A2 Motorway, Warsaw - Kukuryki, section "Lubelska intersection" - start of the Minsk Mazowiecki ring road, section II, aprox. extension 9 km
Excavación: 290.000 m3
Year: 2018
Cliente: POLAQUA Sp. Z o.o.
NAZACARA - HITO IV ROAD / SECTION III, SANTIAGO DE MACHACA - HITO IV, (BOLIVIA)
Client: Copasa
Year: 2019
Excavation: 2.054.360 m3
SONAREF REFINERY PROJECT LOBITO, (LOBITO – ANGOLA) – YEAR 2013 – 2016. 13.500.000 m3
Realization of excavation in landfill and transport to landfill. Volume: 13.500.000 m3
Values: $ 53.643.452,25
Earthworks in preparation for the implantation of the largest oil processing facility of Angola.
CHIRONTA DAM, VALLE DEL LLUTA, ARICA AND PARINACOTA REGION (CHILE)
Client: CONSORCIO EMBALSE CHIRONTA S.A. (el consorcio está formado por las empresas Dragados y Besalco)
Year: 2018
Excavation: 3.000.000 m3
A54 MOTORWAY - LUGO - SANTIAGO. LAVACOLLA - ARZUA, GALICIA (SPAIN) AÑO 2015 – 2.500.000 m3
Client: Dragados
Year 2015
Excavation: 2.500.000 m3
EASTERN CORRIDOR ROAD – YENDI – GUSHIEGO (GHANA)
Client: ODEBRECHT-ANDRADE.
Year: 2014
Excavation: 2.400.000 m3
Platform construction, access roads and the 192 MW combined cycle electric power plant foundation excavations, Aboadze (Ghana)
Client: Metka S.A.
Area: 100.000 m2
Excavation: 580.000 m3
Year: 2017-2018
Value 3.200.000 USD
M11 PPP GOREY TO ENNISCORTHY BYPASS (IRELAND)
Client: EJV BAM - DRAGADOS
Year: 2016
Excavation: 5.500.00 m3
DAIVOES DAM. HYDROELECTRIC EXPLOITATION OF THE TAMEGA RIVER - RIBEIRA DE PENA (PORTUGAL)
Client: ACE FERROVIAL - MSF.
Year: 2017
Excavation: 1.000.000 m3
Construction, Operation and Maintenance of the Major Works of Water Consolidation and Infrastructure for Irrigation of las Pampas de Siguas - II Stage.
Client: Constructora LAS PAMPAS DE SIGUAS.
Year: 2017
Excavation: 3.500.000 m3
PUENTE ARCE - AIQUILE - LA PALIZADA ROAD. SECTION III PUENTE TAPERAS - LA PALIZADA (BOLIVIA)
Client: CONSTRUCCIONES RUBAU S.A. SUCURSAL BOLIVIA.
Year: 2016
Excavation: 2.500.000 m3
Client: POLAQUA - DRAGADOS
Year: 2017
Excavation: 700.000 m3
“Improvement and Conservation Concession of Route 43”, COQUINBO REGION (CHILE)
Ubicación: Ubicado en la Región de Coquimbo al norte de la ciudad de Santiago, la Ruta 43 se emplaza en las Provincias del Elqui y Limarí. Conecta la Ciudad de Ovalle con la Ciudad de Coquimbo.
Excavation (soils): 1.500.000 m3
Excavation (rock): 300.000 m3
Embankment: 554.000 m3
Value: 8.800.000 EUR
Client: EJV BAM - DRAGADOS.
Year: 2016
Excavation: 700.000 m3
A-21 MOTORWAY JACA-L.P. TO NAVARRA. SECTION SIGÜES INTERSECTION-TIERMAS INTERSECTION, YESA (SPAIN)
Client: VIAS Y CONSTRUCCIONES S.A.
Year: 2018
Excavation: 2.453.974 m3
“CONVERSION TO URBAN STANDARD OF THE SANTIAGO ACCESS ROAD ROUTE 5 NORTH, METROPOLITANA REGION”
Excavation (soils): 500.000 m3
Excavation (rock): 16.000 m3
Embankment: 1.000.000 m3
Value: 9.000.000 EUR